Relevant Experience

Stony Batter Estate.   

Upgrading and maintaining 9.0km of metal roads throughout the estate including drainage and the placement of rip rap into open drains to protect the embankments from erosion.

4 month contract period.

 

Rodney District Council – Waiteitei Rd Seal Extension.        

This project was a 3.5km Seal Extension which involved earthworks, drainage, pavement construction, sealing and traffic services.

16 week construction period. Job was completed two months ahead of schedule.

 

Stony Batter Estate.   

Earthworks carried out on two large commercial building sites.  4.7km formation of new roading and 12.5km maintenance of existing roads and associated drainage.  Construction of a new concrete Ford.

7 month contract period.

 

State Highway Rehabilitation.    

State highway Rehabilitation is an ongoing project which includes rip and remakes, overlays, drainage work, digouts, scour protection, slip removal and any emergency work.

Ongoing projects.

 

Kaipara District Council – Mititai Road AWPT.     

This project was an Area Wide Pavement Treatment of approximately 0.92km which involved earthworks, drainage works, pavement construction, sealing and traffic services.

4 week construction period..

 

Kaipara District Council – Oneriri Road Seal Extension.       

This project was a 3.76km Seal Extension from Kira Rd to Parekura Rd which involved earthworks, drainage, pavement construction, sealing and traffic services.

10 week construction period.

 

 

Kaipara District Council – Mititai Road AWPT.     

This project was an Area Wide Pavement Treatment of approximately 1.64km which involved earthworks, drainage works, pavement construction, sealing and traffic services.

10 week construction period.

 

Rodney District Council – Pakiri Road Seal Extension. 

This project was a 1.5km Seal Extension which involved earthworks, drainage, pavement construction, sealing and traffic services.

8 week construction period.

 

Kaipara District Council – Moir Street AWPT.      

This project was an Area Wide Pavement Treatment of approximately 1.0km which involved drainage works, pavement construction, sealing and traffic services.

8 week construction period.

 

Rodney District Council – Matakana Valley Rd Seal Extension.     

This project was a 2.1km Seal Extension which involved earthworks, drainage, pavement construction, sealing and traffic services.

20 week construction period.

 

North Shore City Council – Coroglen Ave Stormwater Upgrade.    

This project was a stormwater upgrade due to severe flooding in some of the lower lying properties, incorporating various drainage products.

4 week construction period.

 

North Shore City Council – Balmain Road Stormwater Replacement.

Replacement of approximately 100 metres of 225mm concrete pipes, manholes and cesspits due to age and infiltration problems.

2 week construction period.

 

Omaha Beach Limited – 11 Lot Subdivision.

This 11 Lot Subdivision is situated in a sand based area with a high watertable.  340m of concrete stormwater pipe and 190m of 150mmø PVC sewer pipe was laid including 14 manholes.  1500m² of concrete ROW and 120m² of footpath was also constructed.

9 week project period.

 

Martins Bay Road Seal Extension.       

As the principle contractor this project consisted of road widening, drainage installation, kerb and channel construction, pavement construction to a sealed standard and 2 coat chipseal.

6 week project period.

 

Auckland Regional Council Parks and Reserves Upgrade.

Upgrade of carparks and roads with ARC’s parks and reserves.  These are undertaken on an as needed basis throughout the year.

Ongoing project period.

 

Bawden and Associates Forest Road Construction.      

All construction of forest roads and skid sites.  This includes earthworks, drainage, pavement construction and rehabilitation and major culvert construction.

Ongoing projects.

 

Southern Paprika Site Development.   

Southern Paprika is a capsicum growing company which developed an extremely large glass house site.  Our involvement consisted of levelling out the glass house site to within 0.5% of gradient.  A deep dam was also constructed to provide continuous water supply to the business.  The site is located on deep peat which had to be handled with care.

6 week construction period.

 

ALPURT Link Road Extension.    

As a subcontractor the project involved bulk supply of basecourse material and placement and compaction of the subbase and basecourse layers.

Undertaken in 2000.

 

Carter Holt Harvey Forest Road Construction.     

The contract with CHH involved clearing of bush, earthworks, road construction, skid and hauler pads, drainage and silt control throughout the Mahurangi, Mangawhai and Topuni Forests.

11 year road maintenance contract.

 

Kaipara District Council – Tara Road Stage 2 Seal Extension.       

This project was a 1.69km Seal Extension which involved drainage works, pavement construction, sealing and traffic services.

8 week construction period.

 

Torea Road Subdivision.    

This 12 lot subdivision involved earthworks, drainage, pavement construction, footpaths, hotmix carriageway and carparks.

7 month construction period.

 

Rodney District Council – Waiteitei Road Seal Extension.

This project was a 4.5km seal extension which involved carrying out earthworks to widen the road.  Construction of new pavement as well as rehabilitating existing pavement by stabilisation, stabilised basecourse overlay and chip sealing.

16 week construction period.

 

Southern Paprika Extension.

The Project involved cut to fill for the glass house area of 15000m³ and a pond excavation of 37000m³,which has the capacity to contain 45 million litres of water.

12 month construction period.

 

Rodney District Council – Northern Seal Extensions.

The projects involve, carrying out earthworks to widen road formation, upgrade the drainage with extensions to existing road culverts, the installation of new kerb and channel to some areas, construction of new pavements by stabilisation of the existing unsealed pavement, granular overlay and chip sealing.

16 week construction period.

 

Rodney District Council – Run Road Seal Extension.    

This project was a 1.5km seal extension which involved extensive earthworks to widen road formation, upgrade of existing stormwater drainage, constructing a new sealed pavement by stabilisation of the existing unsealed road placing a granular layer, stabilising the overlay and chip sealing.

8 week construction period.

 

Rodney District Council – Pakiri Roading Upgrades.    

This contract is for constructing two separate road upgrade projects in the Pakiri area, Northern Ward Rodney District Pakiri Road (near Rahuikiri Road) 1.3km seal extension Pakiri Road (Higgins Hill) 1.1km area wide pavement treatment.

These two projects typically involve carrying out minor earthworks to widen road formation, minor drainage works, installation of kerb and channel construction of new pavements by stabilization of the existing pavement, stabilized granular overlay and chip sealing.

10 week construction period.

 

Kaipara District Council – Tomarata Road, Molesworth Drive and Gibbons Road Rehabilitation.

The three projects involved earthworks, drainage works, installation of concrete dish channel, stabilized pavement construction, sealing and traffic services.

25 week construction period.

 

Auckland Transport – Matakana Valley Road RP7530 Slip Rehabilitation.

This project involved the construction of two timber retaining walls, one built across the slip face (overslip) & the other to support the cut batter for the new road alignment (underslip).

Initial 4 week construction period was extended to 16 weeks.